Apartment wiring devices · Practical guides
Electrical quantity takeoff glossary: legends, blocks, Xrefs, BOQs and identifiers
Designers, electrical contractors and materials teams sometimes use different terms for the same work. This glossary brings together the terms used in Voltix’s practical guides so you can check unfamiliar wording as you read.
Drawing terms
- legend
- A table explaining drawing symbols, item names, specifications and mounting heights. It is the starting point for a quantity takeoff. How to read the legend
- Symbol
- A defined graphic used to represent a device, such as an outlet or switch, on a drawing.
- Block
- A CAD object that groups lines and text into one object. Device symbols are often blocks, which can be counted efficiently by block name.
- Layer
- A layer groups CAD drawing content by system or purpose. Devices on hidden layers may not be visible.
- External reference (Xref)
- A feature that loads another drawing as a background. If an electrical drawing uses an architectural Xref, missing reference files can leave the walls invisible. DWG and DXF differences
- Model space / paper-space layouts
- Model space is the full-size drawing workspace; a layout is a sheet arranged for printing. Several floors may be drawn side by side in one model space.
- Revision (Rev.)
- A number or label assigned to a drawing revision. Mixing drawings with different revisions can produce incorrect quantities. Drawing revision control
- Enlarged views/details
- An enlarged drawing of part of a plan. Repeated devices on plans and details are a common source of duplicate counts. Causes of duplicate counts
Takeoff terms
- Quantity takeoff
- Measuring material counts, lengths or areas from drawings. This guide covers only the number of wiring devices.
- Wiring devices
- A collective term for wall- or floor-installed devices providing electrical power or communications, such as power outlets, switches and communications outlets.
- residential unit
- A plan for one dwelling-unit type. Multiply its quantities by the number of applicable dwellings to calculate building totals.
- Unit-type schedule
- A table assigning a dwelling-unit type to each building, floor and unit. It also identifies mirrored units and first- or top-floor exceptions. Calculate building totals
- common area
- Areas outside dwelling units, such as corridors, stairs, elevator halls, underground parking, plant and electrical rooms and rooftops. Count them separately from dwelling-unit quantities. Common-area omissions
- Identifier
- A unique device reference in the schedule, such as 101-K-07, that connects its row to its drawing location.
- Evidence
- A record of each device’s item classification and the reason for it. It provides the basis for review. Review checklist
- Review required
- A flag for an item that needs clarification from the designer or site team before ordering because the drawing alone is insufficient.
Estimating and ordering terms
- Unpriced BOQ
- A bill listing item names, specifications and quantities with unit prices left blank for the bidder to complete. Compare it with quantities counted from the drawing. Unpriced BOQ comparison
- BOQ(Bill of Quantities)
- The English term for a bill of quantities, used in international projects and documents from overseas clients.
- quantity schedule
- A schedule of item quantities taken from drawings. These are not necessarily the quantities to order.
- Allowance (loss/reserve)
- Extra quantities added for damage, loss or site changes. The rate depends on the item and company policy. Drawing and order quantities
- Part number
- A manufacturer’s unique product reference. Grounded double-socket outlets can have different part numbers depending on manufacturer, series and color.
- Units (each, set, lump sum)
- Each counts individual items; a set counts a specified group of items; a lump sum counts the entire stated scope as one. Align these units before comparing quantities.
- Faceplate
- The faceplate covering an outlet or switch. It is often ordered separately from the device itself.
Suggest a term
This glossary collects terms Voltix frequently explains during reviews. Sites and companies may use them differently. To report a missing term or a different usage, Contact. After checking, we will update the article and show the revision date.
Sources and scope
This article provides general guidance on reviewing apartment wiring-device quantities. For project decisions, the relevant drawing legend, revision information, specifications and contract scope take precedence. See our Editorial review and correction policy.
Technical references:Scope and limitations of the published drawing and Excel examples · Report an error or ask about supported scope